Yes. There are two ways you can do this.
From the Database Builder, select the Pressure point, from the Right-Click menu, open the properties and go to the Alarms tab. Now add an alarm by selecting its checkbox and then go to the detail panel for this alarm to set up the email information.
If you decide to receive Reset or ACK via email as well, you will need to set up the email server connection settings in the Project configuration wizard
This option is user-specific and can be accessed during runtime from the real-time viewer.
Open the real-time viewer. From the Custom views, add a new User notification view. When this view opens, click on the “Add” or right-click on the screen to add a new notification.
Enter all necessary parameters to send an email when the value of the pressure point exceeds your set point.